FERC issues final EIS for 393.3-MW Swan Lake North Pumped Storage Project

Swan Lake EIS

Federal Energy Regulatory Commission staff have issued a final environmental impact statement (EIS) for the licensing of Swan Lake North Hydro LLC’s proposed 393.3-MW Swan Lake North Pumped Storage Project.

The primary issues associated with licensing the Swan Lake North project – to be located in Klamath County, Oregon -- are effects of construction and operation on soils, water quality, terrestrial resources, recreation and land use, and, most significantly, cultural resources of importance to the Klamath Tribes.

In the final EIS, FERC staff recommended the staff alternative, which consists of measures included in Swan Lake North Hydro’s proposal, as well as many of the recommendations made by county, state and federal agencies, and some additional measures developed by the staff.

Swan Lake North Hydro filed an application on Oct. 28, 2015, for construction and operation of the closed-loop Swan Lake North Project. Water to initially fill the reservoirs and to replace water lost to evaporation and seepage would come from groundwater supplied by the local groundwater agricultural pumping system and delivered to the lower reservoir via an existing underground agricultural irrigation network.

The proposed project would consist of a new upper and lower reservoir, a high-pressure steel penstock between the upper reservoir and the powerhouse, a powerhouse with generating/pumping facilities, three low-pressure steel penstocks from the powerhouse to the lower reservoir, a transmission line and substation, access roads to the lower and upper reservoirs, and accompanying facilities.

The project would occupy 730 acres of federal land administered by the U.S. Bureau of Land Management and the U.S. Department of Interior’s Bureau of Reclamation, and 1,310 acres of state, county and private lands.

Click here to view the complete EIS.



Related Articles

FERC chairman appoints Gadani, Gentry to new positions

Federal Energy Regulatory Commission (FERC) Chairman Neil Chatterjee has appointed Jignasa Gadani as director of the Office of Energy Policy and Innovation (OEPI) and Lindsee Gentry as deputy director of the Office of External Affairs (OEA).

FERC issues preliminary permit to study 1,200-MW Southeast Oklahoma Pumped Storage project

The Federal Energy Regulatory Commission has issued a preliminary permit to Southeast Oklahoma Power Corporation to study the feasibility of the proposed 1,200-MW Southeast Oklahoma Pumped Storage Hydroelectric Project.

FERC takes a firm stand in PG&E bankruptcy filing

The California-based utility requested that a federal bankruptcy court prevent FERC from enforcing the conditions of the more than 380 power purchase agreements (PPAs) that the utility may want to exit under its Chapter 11 bankruptcy filing.

Sign up for your free subscription to the HydroWorld Weekly e-newsletter