Three firms to refurbish generating units at Swiss 4.5-MW Charmey

Three firms to refurbish generating units at Swiss 4.5-MW Charmey


BULLE, Switzerland 11/16/11 (PennWell) -- Swiss utility Gruyere Energie SA has named three companies to refurbish generating units at the 4.5-MW Charmey hydroelectric project on Switzerland's Jogne River.

Gruyere Energie took bids in June to renovate and automate three generating units. The utility produces nearly 12 percent of its electricity from Charmey, which was built in 1893 and relocated in 1957.

Grimsel Hydro, Kraftwerke Oberhasli AG, of Innertkirchen, Switzerland, received a contract worth 1.66 million francs (US$1.81 million) to refurbish the three turbines.

Gruyere Energie awarded a contract worth 953,550 francs (US$1 million) to Gebruder Meier of Zollikofen, Switzerland, to refurbish the three generators.

ABB of Birr, Switzerland, received a contract worth 853,200 francs (US$930,062) for control group, automation, and pipe work.

There were seven bidders for each of the three lots.

 


Follow HydroWorld on Twitter

Latest Articles


HydroWorld Article Categories:

Environmental Regulation & Policy
Hydro Industry News Tenders & Ferc Notices
Technology & Equipment World Regions
Dams & Civil Structures Buyer's Guide
Hydro Review Current Issue Table of Contents
Hydro Review Worldwide Current Issue Table of Contents
Hydro Industry Archives

Advertisement