• Connect With Us:
  • Hydro Review

    Project Spotlight: Developing 7.5-MW Youngs Creek in Washington State

    Successful completion of the 7.5-MW Youngs Creek project in Washington State shows it is possible to develop new small hydro facilities that are both cost-effective and meet high environmental standards. The project has been operating since October 2011.

    By Neil Neroutsos

    The 7.5-MW Youngs Creek hydro project, which began operating in October 2011 about 4 miles south of the city of Sultan in Washington State, generates an average of 2.5 MWh per year of clean, reliable, renewable power for the Snohomish County Public Utility District. The PUD developed this project on a quick timeline of just 2.5 years and at a total cost of $29 million. It will provide power to more than 2,000 homes, on average, in Snohomish County PUD's service area.

    In February 2012, the Renewable Energy World network, which includes five print magazines and four websites, presented project owner Snohomish County PUD its Project of the Year Award for hydro. To be eligible for an award, a project needs to have been completed in 2011 in North America and make a significant impact on the entire renewable energy industry. When judging the finalists, network editors considered the technology that was employed, as well as the projects' impact on the industry at large and on the communities in which they were installed.

    Below is the story behind the development of Youngs Creek, the first new hydroelectric plant built in Washington State in nearly 20 years.

    Choosing the project

    Despite the recent economic slowdown, Snohomish County PUD, located north of Seattle in Washington State, expects rapid growth, adding up to 40% to its customer base over the next 20 years. The utility currently serves 320,000 customer accounts in urban, suburban and semi-rural communities. Its elected Board of Commissioners made a commitment as part of its climate change policy in 2007 to meet additional load growth through aggressive energy conservation and renewable energy sources. Small hydropower projects are key components of the utility's energy mix.

    "We want to develop these resources to the extent possible within our own service territory," said Snohomish PUD General Manager Steve Klein. "By doing so, we can better determine and guide our own destiny and provide economic development and jobs within our own community."

    The story behind the Youngs Creek facility demonstrates that new small hydropower sites can be developed in ways that make them cost-effective while still meeting high environmental standards.

    The powerhouse for the 7.5-MW Youngs Creek project in Washington State is a concrete block structure with a metal roof. It contains a single two-jet horizontal Pelton turbine.
    The powerhouse for the 7.5-MW Youngs Creek project in Washington State is a concrete block structure with a metal roof. It contains a single two-jet horizontal Pelton turbine.

    The utility purchased the land for its Youngs Creek project in 2008. The site had an existing license from the Federal Energy Regulatory Commission, which was originally issued to Puget Sound Energy. The previous site owner had developed some initial designs but never moved forward on the project. Snohomish PUD officials worked with FERC to assume the license, with the condition that the hydropower project would be built by the end of 2011.

    As they assessed the Youngs Creek site, PUD staff saw several benefits. Like other PUD small hydropower projects, it is located outside of sensitive areas, such as designated wilderness lands. The powerhouse and intake are above a natural barrier, a waterfall, so there are no issues related to migrating fish. The project also is located close to two other PUD hydropower projects - the utility's 650-kW Woods Creek and 112-MW Jackson projects - so it can be easily operated and maintained by existing staff.

    "We see small hydropower as a resource that's competitively priced or cheaper than other green energy sources," said PUD Manager of Generation Engineering Scott Spahr. "These projects give us greater flexibility with our power supply as they're locally generated, reliable resources that provide energy at times of the year when it's needed the most."

    The Youngs Creek project will generate the highest levels of energy during the winter months, the utility's highest demand period. In drier summer months, it will operate in limited capacity or be shut down temporarily for maintenance.

    The short FERC project deadline put the PUD on the fast track, but the utility was able to tap existing staff and assemble a project team to meet multiple construction deadlines. Extremely wet conditions in fall 2010 also created challenges in the timing of some construction.

    Construction work

    Snohomish County PUD began project design work in 2008. EES Consulting of Kirkland, Wash., was the design consultant for the project. The utility engaged with multiple stakeholders during its planning process, including local tribes, environmental groups and regulatory agencies. It worked closely with the Washington Department of Fish & Wildlife, other state and federal agencies and local tribes to ensure that the project was designed to provide adequate levels of river flow and fish protection.

    In 2009, they obtained permits from the county, U.S. Army Corps of Engineers and regulatory agencies and began material procurement.

    The PUD broke ground on the project in 2010 and started construction of the intake, penstock, powerhouse, and transmission line. The 12-foot-long diversion weir across the river impounds a 0.25-acre area of water.

    A 12-foot-long diversion weir impounds a 0.25-acre area of water, which is fed through an intake into a penstock that drops 920 feet in elevation to the powerhouse to provide flow up to 120 cubic feet per second.
    A 12-foot-long diversion weir impounds a 0.25-acre area of water, which is fed through an intake into a penstock that drops 920 feet in elevation to the powerhouse to provide flow up to 120 cubic feet per second.

    The 14,300-foot-long underground penstock was 48 to 51 inches in diameter and was made of welded steel supplied by Ameron International of Pasadena, Calif. The penstock drops 920 feet in elevation from the intake to the powerhouse to provide flow up to 120 cubic feet per second. The powerhouse is a concrete masonry unit (concrete block) structure with a metal roof. It measures 60 feet by 40 feet and is 35 feet high.

    TEK Construction of Bellingham, Wash., was general contractor for the construction work, and Strider Construction Co. of Bellingham served as civil contractor for the earthwork and pipeline installation. Gilbert Gilkes and Gordon of Kendal, Cumbria, United Kingdom, supplied the single two-jet horizontal Pelton turbine for the plant, while Hyundai Ideal Electric of Mansfield, Ohio, supplied the synchronous generator with exciter. North American Phoenix Energy Services of Phoenix supplied the powerhouse controls. Hawkeye Construction of Hauppauge, N.Y., built the transmission system.

    The community of Sultan, about 4 miles from the project site, received an economic boost during the construction phase, as contractors' crews coming through the area increased revenues for local hotels, restaurants and various retailers.

    Work to be completed in 2011 involved additional electrical/mechanical work, completion of the penstock and connection to the grid at the Sultan substation.

    In total, development of the Youngs Creek project cost $29 million, which was financed with bonds.

    Small hydro potential

    Snohomish PUD is assessing several additional small hydropower sites for potential development in the next five to 10 years. The projects' potential generating capacity ranges from 2 to 30 MW. If fully developed, the collective energy output could serve tens of thousands of PUD customers.

    As was the case with the Youngs Creek site, the PUD has been proactive in engaging community members and regulatory agencies as it considers new projects. In many cases it can bring improvements to the community as it develops projects.

    For example, a project on the Skykomish River in Western Washington, now in the study phase, could include improvements to a state-operated fish trap and haul facility. The state uses trucks to transport fish 4 miles upstream around a set of waterfalls, providing more than 90 miles of additional spawning habitat for fish. The state, strapped for funding to upgrade the facility, could get critical support from the PUD for the fish operation if the hydropower project is completed.

    This waterfall provides a natural barrier just below the powerhouse and intake, meaning there are no issues related to migrating fish at the 7.5-MW Youngs Creek project.
    This waterfall provides a natural barrier just below the powerhouse and intake, meaning there are no issues related to migrating fish at the 7.5-MW Youngs Creek project.

    "In assessing potential sites, we're especially mindful of anadromous fish populations, hydrology, geology, environmental issues and access to existing roads and transmission lines," said PUD Assistant General Manager of Water, Generation and Corporate Services Kim Moore. "We want to balance energy generation with the need to protect river flows, water quality and cultural resources."

    The PUD's small hydropower facilities are designed as run-of-river projects, which divert a portion of the water to a pressurized pipeline that delivers it to a turbine downstream for energy production. Given rainfall patterns in the region, the generating output is naturally maximized during times of high energy demand. These facilities also complement other intermittent energy sources, such as wind and solar.

    PUD small hydropower sites require approval by FERC. For its planning purposes, the utility expects each project will take five to seven years from the application stage to completion of construction.

    The small hydro facilities currently do not qualify under Washington's renewable portfolio standard, although a recently proposed state bill sought to include new hydro projects of 5 MW average or less. It didn't pass. The PUD and other utilities have supported such legislation.

    Hydropower is an essential source

    For decades, the bulk of the PUD's energy has come from clean, renewable hydroelectric power. Most of this energy is purchased from Bonneville Power Administration, which markets wholesale power generated in the Columbia River Basin. Hydropower has provided a low-cost, reliable source of energy for the people of the Pacific Northwest.

    In addition to Youngs Creek, the PUD operates two other hydropower plants in Snohomish County. The Jackson Hydroelectric Project, north of Sultan, was built in 1984. The Woods Creek Project, north of Monroe, was purchased from a private party and upgraded in 2008. Along with BPA energy, about 80% of the PUD's energy portfolio now comes from hydropower.

    The PUD also is proactively researching and acquiring other clean, renewable resources as part of its effort to meet growing needs through conservation and renewable energy sources. The utility has one of the most comprehensive solar energy programs in the Northwest, which offers incentives and technical resources for customers. Snohomish County PUD also contracts for wind energy from three facilities in Oregon and Washington. And the utility is at the forefront of researching tidal and geothermal energy development in the Northwest, which are promising resources to help it meet even more of its needs with renewable energy.


    Benefits of Small Hydropower

    Snohomish County Public Utility District in Washington State sees several important benefits of small hydro projects:

    - Non-polluting renewable source, with no heat or noxious gas releases;

    - Generating output is naturally maximized during times of high energy demand, which complements intermittent sources such as wind, solar and other PUD energy sources;

    - Provides a locally generated resource right in the PUD's backyard, providing greater flexibility with its energy supply and minimizing the need for new transmission systems;

    - Very competitive in price compared to other renewable sources;

    - Located outside of sensitive are-as, such as designated wilderness sites, and above natural barriers so as not to affect migrating fish populations. In some cases, there are resident trout in upper reaches of the creeks/rivers, but they are already isolated due to the falls and other conditions; and

    - Have long lives - many facilities have lives of more than 100 years.

    Neil Neroutsos is the media liaison for Snohomish County Public Utility District.

    More HR Current Issue Articles
    More HR Archives Issue Articles

    Hydro Review Past Issues

    Issue 10

    12/01/2013

    Volume 32
    Issue 10
    Issue 9

    11/01/2013

    Volume 32
    Issue 9
    Issue 8

    10/01/2013

    Volume 32
    Issue 8
    Issue 7

    09/01/2013

    Volume 32
    Issue 7
    Issue 6

    07/01/2013

    Volume 32
    Issue 6
    Issue 5

    06/01/2013

    Volume 32
    Issue 5
    Issue 4

    05/01/2013

    Volume 32
    Issue 4
    Issue 3

    04/01/2013

    Volume 32
    Issue 3
    Issue 2

    03/01/2013

    Volume 32
    Issue 2
    Issue 1

    01/01/2013

    Volume 32
    Issue 1

    Hydro Industry Financials

    Buyers Guide Products

    Micro Hydro Power Generating Equipment

    TOSHIBA’s Micro Hydro series comprise five stan...

    Andritz Compact HydroTurbines

    A modular design for the small hydro power rang...

    Turbines, Francis

    Voith supplies cost-effective Francis units in ...

    Most Read Articles

    Recent Comments

    Buyers Guide Companies

    Wiegert & Baehr Maschinenbau GmbH

    Offers Pelton and Francis turbines to 5000kW, K...

    Sigma Engineering Ltd

    Sigma provides services in hydrology and all as...

    GUGLER Water Turbines GmbH

    Develops and supplies water turbines and small ...

    TURAB Turbin & Regulatorservice AB

    Manufactures, refurbishes and maintains hydro t...

    Schmidt Industries

    Manufacturer of valve assemblies, Rotor and She...

    Continuing Education

    Professional Development Hours
    To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

    12/01/2013
    Volume 32, Issue 10
    file
    11/01/2013
    Volume 21, Issue 6
    1311hrw-cvr

    Archived Articles

    2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
    Hydro Review Past Issues

    Premium Content AD Promo Space