U.S. awards dam safety site stabilization at 270-MW Wolf Creek Dam

Corps of Engineers Logo

The U.S. Army Corps of Engineers awarded a $950,088 contract to Aspen Construction Co. for dam safety site stabilization work at 270-MW Wolf Creek Dam in Kentucky.

The Corps' Nashville District took bids for the work in June.

Aspen, of Hackensack, Minn., is to perform site stabilization at the hydropower project including downstream berm regrading, a trench drain system, tailwater piping removal, and excavation and disposal area seeding.

Identifying the earthfill and concrete gravity dam as critically near failure or having extremely high life or economic risk, the Corps awarded dam safety contracts in 2011 for a grout curtain and in 2013 for geotechnical engineering. Also in 2013, the Corps poured the last of 1,200 concrete piles required to mitigate seepage through the karst geology deep in Wolf Creek Dam's foundation.
 

Related Articles

U.S. seeks spillway gates rehabilitation at 34.5-MW Hills Creek hydro project

The U.S. Army Corps of Engineers seeks bids to rehabilitate three spillway gates at the 34.5...

Dam Safety & Security

Collection of articles covering safety and security of dams and civil structures

Equipment Failure Survey Quantifies Outage Impacts

The cost and schedule impacts of delaying investment in hydropower equipment to the point of...

Flow Tests Lead to Increased Efficiencies and Benchmark Measurements

Measuring water flow to generating units at the 1,520-MW Manic-5 powerhouse, with the goal o...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

07/01/2015
Volume 34, Issue 6
07/01/2015
Volume 23, Issue 4

Buyers Guide Products