Corps provides guidance on Section 408 approval process

Corps of Engineers Logo

The U.S. Army Corps of Engineers has issued an Engineering Circular that provides guidance on how it will process requests from non-Corps entities to alter USACE-owned civil works projects.

The guidelines, available in the circular here, are pursuant to the Corps' Section 408 permitting process and applicable to all private, public, tribal and other federal groups wishing to use USACE properties.

Section 408 authorizes the Secretary of the Army to grant for the alteration, occupation or use of USACE properties, if the Secretary determines the activity "will not be injurious to the public interest and will not impair the usefulness for the project."

As defined by the Engineering Circular, the Corps' Section 408 procedures will be grouped into nine steps, including: pre-coordination, written request, required documentation, district-led Agency Technical Review, Summary of Findings, division review, USACE headquarters review, notification, and post-permission oversight.

The Corps said the guidance will not only be applied to conventional projects being developed in combination with unpowered USACE dams, but also non-conventional projects, such as hydrokinetic facilities, that would use civil works structures like jetties, levees and navigation channels.

For more policy and regulation news, visit here.
 

Related Articles

Turkey seeks hydropower project efficiency studies

Turkey's energy ministry invites expressions of interest from consultants to assess energy e...

Partners break ground on 9.7-MW Datara small hydroelectric project in Indonesia

A three-party joint venture recently broke ground on the 9.7-MW Datara small hydropower plan...

U.S. Department of Commerce official Chandra Brown joins HydroVision keynote lineup

Organizers of the world's largest hydroelectric power event are pleased to announce the addi...

Nepal seeks rehab construction of 640-kW Sundarijal hydro project

Nepal Electricity Authority (NEA) seeks bids for construction and equipment rehabilitation o...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

06/01/2015
Volume 34, Issue 5
03/01/2015
Volume 23, Issue 2

Buyers Guide Products

Buyers Guide Companies

Studio Ing G Pietrangeli Srl

We have 49 years of international experience. 1...