Finnish utility Kemijoki Oy has selected the Caverion Corporation to increase the capacity at its 110-MW Seitakorva hydropower plant.

Caverion said the project includes the refurbishment of Seitakorva's machinery, and electrical and automation systems. The work will begin later this summer with Caverion responsible for design, installation and management services.

"The project is of high significance for Kemijoki Oy as it will make Seitakorva’s machinery one of the largest hydropower machines generating balancing power in Finland," Kemijoki Oy president and CEO Tuomas Timonen said.

Preparations have already begun, the utility said, with as many as 50 Caverion employees to work on the project before it is completed in November.

The overhaul is part of an extensive Kemijoki Oy plan to increase its cumulative generating capacity and decrease its environmental impact by overhauling its machinery. The company is Finland's leading producer of hydroelectric power with more than 1,100 MW of installed capacity spread across a fleet of 20 projects.

HydroWorld.com reported the company had received a Nordic Investment Bank loan to help pay for the refurbishment program last year.

For more rehabilitation and upgrade news, visit here.

HydroVision International 2014 Keynote Speakers

Presenting the HydroVision International 2014 Keynote Speakers

Check out a slideshow covering the keynote speakers at the HydroVision International 2014 conference and exhibition

Click Here >>

Hydro Industry Financials

Buyers Guide Products

Modernization and renewal

TOSHIBA contributes to numerous modernizations ...

TES VSETIN Service Activities

Installation and initiation Operator training W...

Generators and Motor Repair

Service Activities: Installation and initiation...

Hydropower Generation Services OnSite

We evaluate each situation and provide turnkey ...

Maintenance & Construction Services

NAES is a leading provider of construction, ins...

Analysis, Repair & Upgrade Spring-bed Hydroelectric Bearings

Pioneer offer you the less expensive option to ...

Most Read Articles

Recent Comments

Buyers Guide Companies

SBIW Inc

Rehabilitation of turbine, generator and auxili...

Shenyang Getai Hydropower Equipment Co Ltd

Manufacturer of steel runner for water turbine,...

Alstom

Alstom provides products and services for turnk...

Ayres Associates

Provides inspection and FERC compliance, rehabi...

HydroWorks Ltd

Designs and manufactures Pelton, Francis and Ka...

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

09/01/2014
Volume 33, Issue 7
cover
07/01/2014
Volume 22, Issue 4
file

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues