Untitled Document

New control system on line at 6.8-GW Grand Coulee hydropower plant

Grand Coulee Dam

A new control system implemented by communications technology company Real-Time Innovations is now operational at the 6,809-MW Grand Coulee hydroelectric plant.

The "RTI Connext DDS" system installed by Real-Time Innovations replaces a previous supervisory control and data acquisition (SCADA) system as part of a U.S. Army Corps of Engineers modernization program.

"The Grand Coulee Dam is a key national asset," RTI CEO Stan Schneider said. "There is perhaps no greater challenge than to simultaneously deliver both state-of-the-art technology and ultra-mature operation."

RTI said the system must control 24 turbine units and 12 pumps, spread across Grand Coulee's four major power plants. The system must also handle three high-voltage transmission switchyards and a fully-redundant control room while distributing up to 300,000 data values reliably over large distances.

"This is perhaps the most challenging and mission-critical control system in the power industry," said Dave Brown, Chief of the USACE Automated Controls and Cyber Security branch. "The RTI middleware implements our communications, module failover, wide-area routing, control room integration, and operator interface. Our extensive tests proved that the new control system is capable of handling all our performance, scale, reliability, and scalability requirements."

For more technology and equipment news, visit here.

Related Articles

U.S. extends call for relays, switchgear for 21.5-MW St. Marys Falls hydro project

The U.S. Army Corps of Engineers has extended the deadline for bids to replace protective re...
Keeyask hydroelectric power project

Canada utility seeks isolated phase bus for 695-MW Keeyask hydro project

Canadian utility Manitoba Hydro seeks bids to supply isolated phase bus for the 695-MW Keeya...

Sweet Success: Rehabilitating Governor Controls at a Century-Old Facility

Upgrading from mechanical to digital controls on venerable hydroelectric generation units op...

U.S. seeks relays, switchgear for 21.5-MW St. Marys Falls hydro project

The U.S. Army Corps of Engineers seeks bids to replace protective relays and switchgear/moto...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

06/01/2015
Volume 34, Issue 5
05/01/2015
Volume 23, Issue 3

Buyers Guide Products