NPC completes underwater work at Agus 6 hydroelectric plant

Philippines Flag

Operations have resumed at the 200-MW Agus 6 hydropower plant after the Philippines' National Power Corp. finished plugging a leak in the dam's blow-off pipe.

The underwater repairs were necessitated after the leak was discovered this past March through a joint effort of Napcor's Dams, Reservoirs and Waterways Management Division and Mindanao Generation plant maintenance personnel.

NPC said that a team was able to seal the leak using a mixture of rocks and cohesive binding material, providing what company officials said is a long-term and permanent solution.

The Philippines' Power Sector Assets and Liabilities Management Corporation (Psalm) announced seven companies were vying to provide upgrades to two of Agus 6's turbines this past August.

For mroe news from Asia, visit here.

HydroVision International 2014 Keynote Speakers

Presenting the HydroVision International 2014 Keynote Speakers

Check out a slideshow covering the keynote speakers at the HydroVision International 2014 conference and exhibition

Click Here >>

Hydro Industry Financials

Buyers Guide Products

Needlefish P150 ROV

Portable system designed for underwater inspect...

Most Read Articles

Recent Comments

Buyers Guide Companies

Global Diving & Salvage Inc

Contractors and government agencies rely on Glo...

Handon Diving Service Inc

J W Fishers Manufacturing Inc

Designs and manufactures underwater search syst...

Eason Diving & Marine Contractors

Provides general contractor, subcontractor, con...

Hydrokarst

Underwater, rope access and confined area contr...

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

09/01/2014
Volume 33, Issue 7
cover
07/01/2014
Volume 22, Issue 4
file

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues