RusHydro announces results of 2013 hydropower project modernization program

RusHydro Logo

A "comprehensive modernization" program of nine hydropower projects through 2013 by Russian utility JSC RusHydro has resulted in 737 MW of new cumulative installed capacity.

The US$942.8 million overhaul project included work at a number of hydroelectric plants, with work including both turbine replacement and rehabilitation, and other mechanical and electrical upgrades.

RusHydro (LSE: HYDR) said the largest volume of work took place in the Volga-Karma cascade, with a new 65 MW unit replacing an old 55 MW unit at the Rybinskaya hydropower project. Meanwhile, a new 54 MW unit was commissioned at Saratovskaya, and Kamskaya, Volzhskaya and Zhigulevskaya each got two modernized units.

In addition, Nizhegorodskaya, Kamskaya, Votkinskaya and Zhigulevskaya all had gates of spillway dams replced, while switchyards were modernized at Rybinskaya, Votkinskaya, Saratovskaya, Maynskaya and others. Construction of a new spillway at the Egorlyskaya plant is also now under way.

Modernizations will continue through 2014, RusHydro said, with turbine units being upgraded at Chebokarskaya, Kamskaya, Zhigulevskaya, Saratovskaya, Volzhskaya, Novosibiriskaya, Miatlinskaya and others.

Switchyard reconstruction at Rybinskaya, Zhigulevskaya and Zelenchukskaya is also planned, with a new spillway to also be built at Egorlykskaya.

For more news from Russia, visit here.

HydroVision International 2014 Keynote Speakers

Presenting the HydroVision International 2014 Keynote Speakers

Check out a slideshow covering the keynote speakers at the HydroVision International 2014 conference and exhibition

Click Here >>

Hydro Industry Financials

Buyers Guide Products

Modernization and renewal

TOSHIBA contributes to numerous modernizations ...

TES VSETIN Service Activities

Installation and initiation Operator training W...

Generators and Motor Repair

Service Activities: Installation and initiation...

Hydropower Generation Services OnSite

We evaluate each situation and provide turnkey ...

Maintenance & Construction Services

NAES is a leading provider of construction, ins...

Analysis, Repair & Upgrade Spring-bed Hydroelectric Bearings

Pioneer offer you the less expensive option to ...

Most Read Articles

Recent Comments

Buyers Guide Companies

SBIW Inc

Rehabilitation of turbine, generator and auxili...

Shenyang Getai Hydropower Equipment Co Ltd

Manufacturer of steel runner for water turbine,...

Alstom

Alstom provides products and services for turnk...

Ayres Associates

Provides inspection and FERC compliance, rehabi...

HydroWorks Ltd

Designs and manufactures Pelton, Francis and Ka...

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

09/01/2014
Volume 33, Issue 7
cover
07/01/2014
Volume 22, Issue 4
file

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues