Eighth unit operating at RusHydro’s 3,000-MW Boguchanskaya hydropower plant

RusHydro Logo

The eighth hydroelectric generating unit at JSC RusHydro’s Boguchanskaya plant began operating Dec. 30.

This brings total installed capacity of all operating units to 1,998 MW, with a working capacity based on reservoir level of 1,362 MW.

The first seven 333-MW units were put into operation during 2012 and 2013. Preparation of the final unit for testing is currently under way. Each unit was manufactured by Power Machines at a cost of US$117.3 million.

From January to November 2013, the Boguchanskaya powerhouse supplied 4,367 GW of electricity to the wholesale and capacity market, RusHydro (LSE: HYDR) says.

Development of Boguchanskaya, on the Angara River in the northern part of Russia’s Krasnoyarsk Region, is a 50/50 joint venture of RusHydro and Russian aluminum company UC RUSAL.

Latest Slideshow

Your Picture Here: Send Us Your Dam Selfie

View Slideshow >>

more slideshows >>   

Hydro Whitepapers

Hydro Industry Financials

Most Read Articles

Recent Comments

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

03/01/2015
Volume 34, Issue 2
1503HRcover
03/01/2015
Volume 23, Issue 2
1503HRWcover

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues

Buyers Guide Companies

Studio Ing G Pietrangeli Srl

We have 49 years of international experience. 1...