RusHydro inaugurates fourth unit at 3,000-MW Boguchanskaya hydro project

Boguchanskaya Hydropower Project

The fourth turbine unit at JSC RusHydro's 3,000-MW Boguchanskaya hydroelectric plant is now in commercial operation, the Russian utility announced this week.

HydroWorld.com reported in September 2011 that each of Boguchanskaya's nine 333 MW hydro turbines was manufactured by Power Machines at a cost of US$117.3 million.

RusHydro said the first three units began commercial operation Dec. 1, 2012, and that the complex had produced a total of 8.6 million kWh through the first week of January 2013.

The project is being developed in partnership with Russian aluminum company Rusal as part of the Boguchanskoye Energy and Metals Complex.

The project is located on the Angara River in the northern part of Russia's Krasnoyarsk Region.

Latest Slideshow

Your Picture Here: Send Us Your Dam Selfie

View Slideshow >>

more slideshows >>   

Hydro Whitepapers

Hydro Industry Financials

Most Read Articles

Recent Comments

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

03/01/2015
Volume 34, Issue 2
1503HRcover
03/01/2015
Volume 23, Issue 2
1503HRWcover

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues

Buyers Guide Companies

Studio Ing G Pietrangeli Srl

We have 49 years of international experience. 1...