ANEEL authorizes commercial operation for Santo Antonio's newest hydro turbine

Santo Antonio Hydro Project

Brazil's electricity regulatory agency ANEEL has authorized the start of commercial operation for the 10th hydro turbine at the 3,150-MW Santo Antonio hydroelectric plant.

The Santo Antonio complex -- not to be confused with a smaller 372 MW Brazilian hydropower project of the same name -- is located on the Medeira River in the Amazon basin. The plant is part of the 3,750-MW Jirau project, which received an operating license from Brazil's Institute of the Environment and Natural Resources (IBAMA) in October 2012.

Santo Antonio's newest turbine unit adds 69.6 MW to the plant's existing 713.5 MW of overall capacity. The turbine is the second in Santo Antonio's Power House II, which is located on the left bank of the Madeira River.

According to operator Santo Antonio Energia, another 17 turbines will enter commercial operation in 2013, totaling 27 generating units in production.

Related Articles

China's State Grid to construct longest transmission line in Brazil as part of Belo Monte hydroelectric project

China's State Grid has been awarded a contract to build and operate a second transmission li...

Brazil seeks regional development plan for hydropower project sites

Brazil's mines and energy ministry invites expressions of interest from consultants to help ...

Norte Energia awards supply contracts for Brazil's 11.2-GW Belo Monte hydroelectric plant

Brazil's Norte Energia has awarded a pair of contracts for the supply of mechanical equipmen...

Cemig has operating right for 242-MW Jaguara hydropower plant revoked

The Brazilian Supreme Court ruled this week that utility company Cemig has no right to renew...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

07/01/2015
Volume 34, Issue 6
07/01/2015
Volume 23, Issue 4

Buyers Guide Products