Switzerland's SBB AG awards contract for small hydropower plant overhaul

Massaboden Small Hydropower Project

Gebruder Meier of Switzerland has won a contract worth US$1.61 million to overhaul two generator units at the 7.6-MW Massaboden small hydropower plant.

The project is owned by a unit of Swiss federal railway company SBB AG, which solicited bids for the work in June.

According to the SBB AG Einkauf Infrastruktur Elektroanlagen und Energie tender, Gebruder Meier will refurbish Units 3 and 4 at Massaboden, which was first built in 1899 at Bisch on the Rhone River in Switzerland's Valais canton.

The two 3.8-MW generators have been in service more than 50 years and require replacement of stator windings and examination, replacement, or repair of other components.

The first unit is to be refurbished in winter 2013-2014, with the other to follow in winter 2014-2015. The work is to be performed in parallel with renewal of controls and the safety system, which were advertised in a separate solicitation.

A unit of Swiss federal railway SBB AG seeks bids for generator overhaul of two units of the 7.6-MW Massaboden hydroelectric project on the Rhone River in Switzerland. Bids are due July 2.

SBB owns a series of hydroelectric projects to power its rail system, including 124-MW Chatelard and 56-MW Amsteg. SBB also is building the 900-MW Nant de Drance pumped-storage project with energy provider Alpiq and Forces Motrices Valaisannes.

For more news from Europe, visit here.

HydroVision International 2014 Keynote Speakers

Presenting the HydroVision International 2014 Keynote Speakers

Check out a slideshow covering the keynote speakers at the HydroVision International 2014 conference and exhibition

Click Here >>

Hydro Industry Financials

Buyers Guide Products

Pump Turbines

For new and upgraded pump-turbines, American Hy...

Rehabilitation and Total Plant Upgrades

Turbine rehabilitation is directed by turbine e...

Weir Turbines, Francis

American Hydro can supply the turbine or the co...

Weir Turbines, Kaplan

Rugged reliability. This is the foundation of o...

Temporary Bulkheading for Valve Replacement

Hibbard Inshore can design, insert, and remove ...

PXL Kaplan Turbine Seals

Provides sealing for Kaplan turbines with seali...

Most Read Articles

Recent Comments

Buyers Guide Companies

Fematics Canada

Engineers and manufactures mechanical seals for...

Gracon Corp

Offers turbine and heavy mechanical installatio...

Paul Willis PE

Conducts hydro turbine related equipment studie...

Leroy Somer

Manufactures alternators from the power range b...

MJ2 Technologies SAS

MJ2 Technologies is the designer and manufactur...

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

06/01/2014
Volume 33, Issue 5
file
07/01/2014
Volume 22, Issue 4
file

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues