Brazil's 192-MW Garibaldi hydropower plant entering operation early

Canoas River

Brazilian developer Triunfo Participacoes e Investimentos has received regulatory approval to begin commercial operation of the main units at the 192-MW Garibaldi hydropower plant.

The go-ahead comes about 16 months before the January 2015 deadline set by the Agencia Nacional de Energia Eletricqa (ANEEL).

Triunfo said about 70% of the project's output has already been sold under a 30-year concession contract for US$58 per/MWh.

Garibaldi will be operated by Triunfo subsidiary Rio Canoas Energia. The project is located on the Canoas River in the southern state of Santa Catarina.

HydroWorld.com reported that Brazil's Bank of Economic and Social Development, BNDES, had paid the second part of a $108.4 million loan to the developer in January.

For more news from Latin America, visit here.

Related Articles

IHA new hydropower report

International Hydropower Association releases 2015 Hydropower Status Report

The International Hydropower Association announces availability of its 2015 Hydropower Statu...

China Three Gorges buys majority shares in two Brazilian hydropower projects

Brazilian infrastructure group Triunfo Participacoes e Investimentos S,A. .has agreed to sel...

Proposal could ease financial burden imposed on hydropower project operators during Brazil's drought

A provisional decree approved by Brazil's legislature yesterday would allow hydroelectr...

Brazil's Colider, Baixo Iguacu hydropower projects receive Copel financing

An earnings statement from Copel shows the Brazilian utility intends to spend about US$100 m...

Recent Comments

Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

Volume 34, Issue 6
Volume 23, Issue 4

Buyers Guide Products