ANEEL authorizes Santo Antonio's 13th hydro turbine

Santo Antonio Hydropower Project

Brazil's Agencia Nacional de Energia Eletricqa (ANEEL) has authorized commercial production from the 13th hydro turbine installed at the Santo Antonio project.

The new 73.2 MW unit will raise the Santo Antonio hydroelectric plant's output capacity to 995 MW -- still shy of the 3,150 MW the project is ultimately expected to produce when completed in November 2015.

Two additional units are currently being tested, according to the Santo Anonio Energia consortium, with another 14 to be added by the end of the year.

HydroWorld.com reported the first of Santo Antonio's 44 turbines began generating power in February 2012. Brazil's Institute of the Environment and Natural Resources (IBAMA) then granted a license for its operation in October.

The US$8 billion project is part of the 6.9-GW Rio Madeira hydropower complex, which also includes the 3,750-MW Jirau hydroelectric plant.

HydroVision International 2014 Keynote Speakers

Presenting the HydroVision International 2014 Keynote Speakers

Check out a slideshow covering the keynote speakers at the HydroVision International 2014 conference and exhibition

Click Here >>

Hydro Industry Financials

Most Read Articles

Recent Comments

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

07/01/2014
Volume 33, Issue 6
file
07/01/2014
Volume 22, Issue 4
file

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues