ANEEL authorizes Santo Antonio's 13th hydro turbine

Santo Antonio Hydropower Project

Brazil's Agencia Nacional de Energia Eletricqa (ANEEL) has authorized commercial production from the 13th hydro turbine installed at the Santo Antonio project.

The new 73.2 MW unit will raise the Santo Antonio hydroelectric plant's output capacity to 995 MW -- still shy of the 3,150 MW the project is ultimately expected to produce when completed in November 2015.

Two additional units are currently being tested, according to the Santo Anonio Energia consortium, with another 14 to be added by the end of the year.

HydroWorld.com reported the first of Santo Antonio's 44 turbines began generating power in February 2012. Brazil's Institute of the Environment and Natural Resources (IBAMA) then granted a license for its operation in October.

The US$8 billion project is part of the 6.9-GW Rio Madeira hydropower complex, which also includes the 3,750-MW Jirau hydroelectric plant.

Related Articles

China's State Grid to construct longest transmission line in Brazil as part of Belo Monte hydroelectric project

China's State Grid has been awarded a contract to build and operate a second transmission li...

Brazil seeks regional development plan for hydropower project sites

Brazil's mines and energy ministry invites expressions of interest from consultants to help ...

Norte Energia awards supply contracts for Brazil's 11.2-GW Belo Monte hydroelectric plant

Brazil's Norte Energia has awarded a pair of contracts for the supply of mechanical equipmen...

Cemig has operating right for 242-MW Jaguara hydropower plant revoked

The Brazilian Supreme Court ruled this week that utility company Cemig has no right to renew...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

07/01/2015
Volume 34, Issue 6
07/01/2015
Volume 23, Issue 4

Buyers Guide Products