Voith commissions pair of turbine units at Ecuador's 42-MW Baba

Ecuador Map

Two Voith Hydro-produced Kaplan turbine units are now in commercial operation at Ecuador's 42-MW Baba hydropower plant.

The Baba facility, operated by utility company Hidroenergetico del Litoral (Hidrolitoral), is part of the Baba Multipurpose Project that also includes the already existing 213-MW Central Marcel de Wind.

Voith said the project is not only intended to help with energy production, but also in regulating the Baba River and improving conditions for agriculture and tourism.

The company said the turbines were the first Kaplan units ever to be installed in Ecuador. In addition to the turbines, Voith also supplied the generator and electrical and mechanical services.

HydroWorld.com reported earlier this month that Voith, along with Alstom, is manufacturing what will become Latin America's largest rotor.

Related Articles

Czech utility awards contract for turbine overhaul at Lipno hydropower plant

Czech utility CEZ has awarded a US$3.4 million contract to CKD Blansko Engineering Inc. to p...

U.S. extends call for HVAC upgrades at 402-MW Dworshak hydro project

The U.S. Army Corps of Engineers has extended the deadline for bids to upgrade the heating-v...

U.S. extends bidding for turbine, pump overhaul at 12-MW Chandler hydro plant

The Bureau of Reclamation has extended the deadline for bids to overhaul a turbine and pump ...

U.S. seeks gates replacement at 80-MW Denison Dam hydro project

The U.S. Army Corps of Engineers seeks bids to replace a flood gate and an emergency gate at...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

06/01/2015
Volume 34, Issue 5
03/01/2015
Volume 23, Issue 2

Buyers Guide Products