Historic New Zealand hydropower plant getting four-year rehabilitation

Waitaki Hydropower Project

Power generator Meridian Energy has announced a four-year, US$34 million rehabilitation of its 90-MW Waitaki hydroelectric plant.

The Waitaki hydropower project was originally completed in 1935 with two 15 MW hydro turbines and has since undergone several expansions to bring the plant to its current capacity. The plant now features seven 15 MW turbine units, though only six are operational.

"The Waitaki power station is a historic part of New Zealand's electricity network," said Neal Barclay, Meridian's General Manager Markets and Production. "Despite it being almost 80 years old, it will continue to provide reliable and sustainable electricity for many generations to come."

The company said it will strengthen the powerhouse -- primarily to make it more resilient against seismic activity -- while maintaining the structure's architectural look.

The rehab project will also reinstate Waitaki's seventh generating unit, which, according to Barclay, "hasn't operated for a number of years."

Work will begin in April, though Meridian said the project should have little effect on the surrounding communities.

The Waitaki hydropower station is one of three Meridian-operated plants along the Waitaki River.

HydroWorld.com reported in January 2013 that Meridian had stopped development of another Waikati River project, which would have added 260 MW of hydroelectric capacity.

For more rehabilitation news, visit here.

Latest Slideshow

Your Picture Here: Send Us Your Dam Selfie

View Slideshow >>

more slideshows >>   

Hydro Whitepapers

Hydro Industry Financials

Most Read Articles

Recent Comments

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

03/01/2015
Volume 34, Issue 2
1503HRcover
03/01/2015
Volume 23, Issue 2
1503HRWcover

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues

Buyers Guide Products

Modernization and renewal

TOSHIBA contributes to numerous modernizations ...

TES VSETIN Service Activities

Installation and initiation Operator training W...

Generators and Motor Repair

Service Activities: Installation and initiation...

Hydropower Generation Services OnSite

We evaluate each situation and provide turnkey ...

Maintenance & Construction Services

NAES is a leading provider of construction, ins...

Turbine-Generator Rehabilitation

Efficiency and cost effectiveness can be upgrad...

Buyers Guide Companies

SBIW Inc

Rehabilitation of turbine, generator and auxili...

Alstom

Alstom provides products and services for turnk...

Shenyang Getai Hydropower Equipment Co Ltd

Manufacturer of steel runner for water turbine,...

Ayres Associates

Provides inspection and FERC compliance, rehabi...

Koncar-Generators and Motors Inc

Develops, engineers, designs, manufactures, tes...