BC Hydro gets approval for John Hart hydroelectric plant replacement

John Hart Generating Station

The British Columbia Utilities Commission has given a go-ahead for the replacement of the 126-MW John Hart hydropower station, HydroWorld.com has learned.

Located on the Campbell River, replacement of the John Hart Generating Station deemed the most cost effective way of addressing a number issues associated with the current 65-year-old hydro plant.

HydroWorld.com reported in July 2012 that the plant's owner, BC Hydro, had short-listed three consortia to construct a 138 MW replacement.

The new John Hart overhaul is expected to cost between US$984 million and $1.18 billion and will include a new replacement intake at the John Hart Spillway Dam, the replacement of an existing 2.1-kilometer tunnel with three 1.8-kilometer pipelines, the construction of a replacement power plant next to the existing one, and building of a new water bypass.

Work on the project is expected to take five years and will create about 400 jobs, according to BC Hydro.

"BC Hydro would like to thank the customer and other stakeholder groups who participated in the regulatory process, government agencies, and local community and business organizations who played a key role in shaping this project," said Chris O'Riley, BC Hydro Executive Vice-President of Generation.

The company said the project will protect fish, reduce John Hart's footprint, power Vancouver Island and decrease seismic risk.

BC Hydro announced it would proceed with environmental and regulatory reviews in Mach 2012.

Related Articles

Kelsey hydro project work

Manitoba Hydro extends call for head cover, hoist frame work at 250-MW Kelsey hydro project

Canadian utility Manitoba Hydro has extended the deadline for bids to perform head cover rep...

Corps awards contract for fixed cone valve for West Virginia's Summersville Dam

The U.S. Army Corps of Engineers has awarded a contract worth $875,000 to Integrated 8(A) So...

U.S. seeks tainter gates replacement at Illinois' Dresden Island Dam

The U.S. Army Corps of Engineers seeks bids to supply as many as four replacement tainter ga...

Pakistan seeks supervision of turbine-generator refurbishment at 1,000-MW Mangla hydro project

Pakistan's Water and Power Development Authority (WAPDA) invites expressions of interest fro...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

06/01/2015
Volume 34, Issue 5
07/01/2015
Volume 23, Issue 4

Buyers Guide Products