Polish utility names supplier for Otmuchow hydropower plant rehab

Energoprojekt Warszawa S.A. has won a contract worth US$12.2 million to replace two turbine-generators at the 4.8-MW Otmuchow hydropower project on Poland's Nysa Klodzka River.

Polish utility Tauron Ekoenergia sp.z.o.o. last sought bids for the work in April.

The Otmuchow hydroelectric plant was constructed in 1933 and is currently undergoing modernization work, which will see Energoprojekt Warszawa replace Units TZ-1 and TZ-2 with 3-MW vertical Kaplan turbines which will have a total installed capacity of 6 MW.

For more rehabilitation and repair news, visit here.

Related Articles

Group announces plan to rehabilitate Guyana's 1.5-MW Tumatumari small hydropower project

A private company has announced plans to rehabilitate the long-defunct 1.5-MW Tumatumari hyd...

U.S. seeks spillway gates rehabilitation at 34.5-MW Hills Creek hydro project

The U.S. Army Corps of Engineers seeks bids to rehabilitate three spillway gates at the 34.5...

Dam Safety & Security

Collection of articles covering safety and security of dams and civil structures

Equipment Failure Survey Quantifies Outage Impacts

The cost and schedule impacts of delaying investment in hydropower equipment to the point of...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

07/01/2015
Volume 34, Issue 6
07/01/2015
Volume 23, Issue 4

Buyers Guide Products