  • Violence causes another work stoppage at Brazil's 11.2-GW Belo Monte hydroelectric plant

    11/15/2012

    Work at Brazil's 11.2-GW Belo Monte hydropower complex has been stopped once again -- this time due to vandalism and worker upheaval at one of the project's three construction sites.

    The Belo Monte Construction Consortium (CCBM) said earlier this week that seven people suffered minor injuries when they attempted to interrupt collective bargaining talks between the construction union and the plant's operator, Norte Energia.

    The workers reportedly set fire to vehicles and mattresses, vandalized offices and canteens, burnt a bus and blocked the Trans-Amazon highway, according to a CCBM statement.

    The setback is only the most recent for the Belo Monte project, which was put on hold in October while opponents of the project began occupying one of the work sites.

    Still, CCBM says the US$17 billion project will be ready for operation in 2015 as originally planned.

    Font Sizes:

    Hydro Industry Financials

    Hydro Financial Markets

    01/01/2013
    Volume 32, Issue 1
    file
    Volume 21, Issue 01
    1301-HRW-cvr

    Most Read Articles

    Archived Articles

    2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
    Hydro Review Past Issues

    Continuing Education

    Professional Development Hours

    To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.