Work complete at Vietnam's 2,400-MW Son La hydroelectric project

All six turbines at Vietnam's 2,400-MW Son La hydropower plant have been connected to the national grid, marking the completion of the nation's largest hydroelectric project.

Work on the US$2.5 billion project began in 2005, with the previous five Francis-type turbines being put into service incrementally throughout the construction process.

Already, Electricity of Viet Nam (EVN) says the Son La complex has contributed about 11,400 GWh to the grid, adding a reported $55 million back to the Son La Province's budget.

The Son La project includes a 453 feet by 300 feet concrete dam that impounds the Da River in north Vietnam.

Also in Vietnam, HydroWorld.com reported in September that Trung Son Hydropower Co. Ltd. is seeking equipment for the 260-MW Trung Son project on the Ma River.

Related Articles

Pakistani officials oppose proposed interest rate hike for 969-MW Neelum Jhelum hydropower plant

Pakistani Prime Minister Nawaz Sharif and his cabinet have refused Chinese demands for highe...

A Positive Outlook for Hydropower

As diverse as the globe itself, the world of hydropower development is a heterogeneous one, ...

Pakistan state seeks bids to build 48-MW Jaggran 2 hydro project

Pakistan's Azad-Jammu-Kashmir State (AJK) seeks bids to build the 48-MW Jaggran 2 hydroelect...

Viewpoint: Securing Skills and Experience: The Route to Commercial Success for MHK

News that Atlantis Resources has struck a deal with Siemens to acquire the entire share capi...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

06/01/2015
Volume 34, Issue 5
05/01/2015
Volume 23, Issue 3

Buyers Guide Products

Buyers Guide Companies