Close 

Andritz wins contract for work at Laos' 1,285-MW Xayaburi project

The Andritz Group has received an order worth US$322 million to$390 million to supply electromechanical equipment for Laos' 1,285-MW Xayaburi hydropower plant on the lower Mekong River in Laos.

The $3.5 billion hydroelectric project is being developed by CH. Karchang Public Co. Ltd., which said in August that it expects to begin constructing a reservoir at the site by the end of the year.

As per the contract, Andritz will deliver seven 175-MW Kaplan turbines, one 68.8-MW Kaplan turbine, generators and governors, automation systems and other equipment.

Andritz says its experience supplying equipment for the Nam Theun 2 hydropower plant -- also located in Laos -- was a key factor in securing this award.


To access this Article, go to:
http://www.hydroworld.com/content/hydro/en/articles/2012/10/andritz-wins-contract-for-work-at-laos-1285-mw-xayaburi-project.html