Untitled Document

Feasibility studies for Serbia's Brodarevo hydropower projects complete

BRODAREVO, Serbia 6/22/12 (PennWell) -- Feasibility studies for Reservoir Capital Corporation's Brodarevo 1 and Brodarevo 2 hydroelectric power plants are complete, HydroWorld.com has learned.

The studies were conducted by independent consultant Energoprojekt Hidroinzenjering Co. Ltd. (EHC) after the hydropower projects were approved by the Serbian government in May. EHC also provided geotechnical work for the project in February.

At that time, the total combined generating capacity of the plants was expected to be 58.4 MW, although that has increased to 59.1 MW.

The total cost of the project is now estimated at about US$185 million, which also includes the construction of new roads and tunnels between the towns of Prijepolje and Bijelo Polje.

Rervoir Capital says the construction time for Brodarevo 1 is four years, and Brodarevo 2 is three years.

Related Articles

Manitoba-Minnesota transmission line

Manitoba Hydro announces final route for transmission line to Minnesota

Manitoba Hydro has announced the final preferred route for its Manitoba Minnesota Transmissi...

CEC gets go-ahead for 40-MW Kabompo Gorge hydropower plant

An implementation agreement signed this week by the Republic of Zambia and the Copperbelt En...

Hedcor receives financing for 68.8-MW Manolo Fortich hydroelectric plant

Aboitiz Power subsidiary Hedcor Bukidnon has secured a loan worth about US$213.2 million to ...

Recent Comments

Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

Volume 34, Issue 7
Volume 23, Issue 5

Buyers Guide Products

Buyers Guide Companies