Feasibility studies for Serbia's Brodarevo hydropower projects complete

BRODAREVO, Serbia 6/22/12 (PennWell) -- Feasibility studies for Reservoir Capital Corporation's Brodarevo 1 and Brodarevo 2 hydroelectric power plants are complete, HydroWorld.com has learned.

The studies were conducted by independent consultant Energoprojekt Hidroinzenjering Co. Ltd. (EHC) after the hydropower projects were approved by the Serbian government in May. EHC also provided geotechnical work for the project in February.

At that time, the total combined generating capacity of the plants was expected to be 58.4 MW, although that has increased to 59.1 MW.

The total cost of the project is now estimated at about US$185 million, which also includes the construction of new roads and tunnels between the towns of Prijepolje and Bijelo Polje.

Rervoir Capital says the construction time for Brodarevo 1 is four years, and Brodarevo 2 is three years.

Latest Slideshow

Your Picture Here: Send Us Your Dam Selfie

View Slideshow >>

more slideshows >>   

Hydro Whitepapers

There is no current content available.

Hydro Industry Financials

Most Read Articles

Recent Comments

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

03/01/2015
Volume 34, Issue 2
1503HRcover
03/01/2015
Volume 23, Issue 2
1503HRWcover

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues

Buyers Guide Companies

Studio Ing G Pietrangeli Srl

We have 49 years of international experience. 1...