Feasibility studies for Serbia's Brodarevo hydropower projects complete

BRODAREVO, Serbia 6/22/12 (PennWell) -- Feasibility studies for Reservoir Capital Corporation's Brodarevo 1 and Brodarevo 2 hydroelectric power plants are complete, HydroWorld.com has learned.

The studies were conducted by independent consultant Energoprojekt Hidroinzenjering Co. Ltd. (EHC) after the hydropower projects were approved by the Serbian government in May. EHC also provided geotechnical work for the project in February.

At that time, the total combined generating capacity of the plants was expected to be 58.4 MW, although that has increased to 59.1 MW.

The total cost of the project is now estimated at about US$185 million, which also includes the construction of new roads and tunnels between the towns of Prijepolje and Bijelo Polje.

Rervoir Capital says the construction time for Brodarevo 1 is four years, and Brodarevo 2 is three years.

HydroVision International 2014 Keynote Speakers

Presenting the HydroVision International 2014 Keynote Speakers

Check out a slideshow covering the keynote speakers at the HydroVision International 2014 conference and exhibition

Click Here >>

Hydro Industry Financials

Most Read Articles

Recent Comments

Buyers Guide Companies

Studio Ing G Pietrangeli Srl

We have 49 years of international experience. 1...

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

06/01/2014
Volume 33, Issue 5
file
07/01/2014
Volume 22, Issue 4
file

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues