    BRODAREVO, Serbia 6/22/12 (PennWell) -- Feasibility studies for Reservoir Capital Corporation's Brodarevo 1 and Brodarevo 2 hydroelectric power plants are complete, HydroWorld.com has learned.

    The studies were conducted by independent consultant Energoprojekt Hidroinzenjering Co. Ltd. (EHC) after the hydropower projects were approved by the Serbian government in May. EHC also provided geotechnical work for the project in February.

    At that time, the total combined generating capacity of the plants was expected to be 58.4 MW, although that has increased to 59.1 MW.

    The total cost of the project is now estimated at about US$185 million, which also includes the construction of new roads and tunnels between the towns of Prijepolje and Bijelo Polje.

    Rervoir Capital says the construction time for Brodarevo 1 is four years, and Brodarevo 2 is three years.

    Hydro Industry Financials

    Most Read Articles

    Recent Comments

    Buyers Guide Companies

    Studio Ing G Pietrangeli Srl

    We have 49 years of international experience. 1...

    Continuing Education

    Professional Development Hours
    To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

    12/01/2013
    Volume 32, Issue 10
    file
    11/01/2013
    Volume 21, Issue 6
    1311hrw-cvr

    Archived Articles

    2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
    Hydro Review Past Issues

    Premium Content AD Promo Space