Minas San Francisco hydro project gets environmental stamp of approval

QUITO, Ecuador 3/30/12 (PennWell) -- Ecuador's 275-MW Minas San Francisco hydroelectric plant has been approved by the country's environmental ministry, sources report.

A resolution passed by the ministry grants an environmental license for the hydropower project, which will reduce carbon dioxide by an estimated 700,000 tons per year.

The US$500 million project is owned by state utility Corporacion Electrica del Ecuador (Celec), and is being funded in part by the China Development Bank.

The project includes a 78-meter-high dam, three Pelton-type turbines and a 45-km transmission line.

Commissioning is expected by the end of 2015.

Related Articles

IHA new hydropower report

International Hydropower Association releases 2015 Hydropower Status Report

The International Hydropower Association announces availability of its 2015 Hydropower Statu...

China Three Gorges buys majority shares in two Brazilian hydropower projects

Brazilian infrastructure group Triunfo Participacoes e Investimentos S,A. .has agreed to sel...

Bolivia utility seeks design, bidding documents for 5-MW Huacata hydro project

Bolivia utility Empresa Electrica Valle Hermoso (EVH) seeks bids to perform final design and...

Proposal could ease financial burden imposed on hydropower project operators during Brazil's drought

A provisional decree approved by Brazil's legislature yesterday would allow hydroelectr...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

07/01/2015
Volume 34, Issue 6
07/01/2015
Volume 23, Issue 4

Buyers Guide Products