  • Interior releases two new studies about Klamath River dam removal

    WASHINGTON, D.C. 1/26/12 (PennWell) -- The controversy surrounding the proposed removal of four dams along the Klamath River in southern Oregon and northern California has a new facet following the release of a two new reports by the U.S. Department of the Interior.

    The first report, titled "Klamath Dam Removal Overview Report for the Secretary of the Interior: an Assessment of Science and Technical Information," is the product of two years of scientific and technical studies conducted to determine the advantages and disadvantages of removing the dams as per the Klamath Hydroelectric Settlement Agreement (KHSA).

    The KHSA seeks the removal of four Klamath River hydropower plants and dams -- 90.338-MW J.C. Boyle, 20-MW Copco 1, 27-MW Copco 2, and 18-MW Iron Gate -- and the transfer of the non-powered Keno Dam to Interior.

    The report is intended to inform the public and legislators of the KHSA's economic, biological, recreational and social impacts prior to a Secretarial Determination, according to an Interior release.

    "The science and analyses presented in these reports are vital to making an informed and sound decision," says Secretary of the Interior Ken Salazar.

    The report is available in its entirety here.

    Interior's second report, titled "Klamath River Basin Restoration Nonuse Value Survey Final Report," is an updated version of its Economics and Tribal Summary Technical Report.

    Proponents of dam removal note that this report anticipates benefits to include an improved salmon and trout habitat and the creation of 1,400 construction jobs during the year it would take to remove the dams. Long-term, the report indicates Klamath basin restoration could add an additional 4,600 jobs.

    Meanwhile, the opposition is supported by the report's indication for increased flooding risk and a cut in electrical production. The report also puts a price tag of more than US$290 million on removal of the dams.

    A summary of key conclusions from both reports is available here.

    Salazar must decide by March 31 whether Interior will recommend the dams' removal. If he does, the governors of Oregon and California will then have 60 days to either concur or veto the plan.

    Hydro Industry Financials

    Buyers Guide Products

    Digital Governor Conversions and Retrofit Kits

    Want to Go Digital? Over the last 10 years we h...

    Standard & Expedited Bearing Repair Services

    Our service and repair department is the longes...

    Canyon Hydro Pelton Turbines

    Canyon Hydro is a leading designer and manufact...

    Manitou Falls 1999

    1'st PTFE-lined thrust bearing shoes delivered ...

    Most Read Articles

    Recent Comments

    Buyers Guide Companies

    Sauer Compressors USA Inc

    ABB Inc/High Current Systems

    Barr Engineering Co

    JM Power Aggregates Ltd

    Owner, inventor and distributor of an environme...

    Hydro Power Services LLC

    Provides service contractor specializing in fie...

    Continuing Education

    Professional Development Hours
    To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

    12/01/2013
    Volume 32, Issue 10
    file
    01/01/2014
    Volume 22, Issue 1
    1401hrw-cvr

    Archived Articles

    2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
    Hydro Review Past Issues

    Premium Content AD Promo Space