• Connect With Us:
  • Windsor Castle going green with new Archimedes hydro turbines

    BERKSHIRE, England (PennWell/12.22.2011) -- A plan that once seemed lifeless is almost a reality following the installation of two Archimedes Screw hydropower turbines at Windsor Castle.

    Developer RWE npower renewables first gained approval for its plan from the Royal Borough of Windsor and Maidenhead Planning Authority of England in 2005, but the company pulled out in 2009 before the project could come to fruition.

    Southeast Power Engineering Limited (SEPE) filled the void, however, and will soon inaugurate a pair of 40-ton steel Archimedes Screws and their accompanying equipment.

    Each 12-meter by 4-meter screw turbine cost the equivalent of US$1.1 million to manufacture and another $1.6 million to install. Together, the turbines will produce 300-KW per hour.

    A $156,000 fish tube has also been installed, giving some species their first passage along the River Thames in more than two centuries.

    It's expected that the Windsor Castle will be operational in early 2012.

    Font Sizes:

    Hydro Industry Financials

    Hydro Financial Markets

    01/01/2013
    Volume 32, Issue 1
    file
    Volume 21, Issue 01
    1301-HRW-cvr

    Most Read Articles

    Archived Articles

    2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
    Hydro Review Past Issues

    Continuing Education

    Professional Development Hours

    To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.