Reclamation EA endorses additional unit for 10-MW Black Canyon

BOISE, Idaho, U.S. 11/1/11 (PennWell) -- The Bureau of Reclamation has issued a final environmental assessment endorsing the addition of a third turbine-generator at 10-MW Black Canyon Diversion Dam, which would at least double the capacity of the Idaho project.

Reclamation said the EA's preferred alternative is addition of a unit of 10 to 12.5 MW to the Payette River project, the first unit to be added to the Federal Columbia River Power System in more than 30 years. The EA included a Finding of No Significant Impact for the proposal.

Black Canyon Diversion Dam is a 183-foot-tall concrete gravity dam with an ogee overflow spillway. Built in 1924, the dam diverts irrigation water to Reclamation's Payette Division through Black Canyon Canal. The two-unit powerhouse supplies electricity to the Southern Idaho Federal Power System.

In addition to increasing project capacity, the new turbine-generator would be designed to generate power during high flow periods as water passes through the turbines rather than over the spillway.

Reclamation said a contract could be issued in late 2012 for the estimated $40 million construction project. The work, funded by Bonneville Power Administration, is expected to start in 2013 and be completed in about two years.

The final EA may be obtained from the Reclamation Internet site at www.usbr.gov/pn/programs/ea/idaho/blackcanyon/index.html.

The Federal Columbia River Power System includes 31 federally owned hydroelectric projects in the Columbia and Snake river basins.

Related Articles

French city seeks construction, operation of Taconnaz small hydro project

The city of Chamonix-Mont-Blanc seeks bids to build and operate the Taconnaz small hydropowe...

HydroWorld Premium Content offers daily business opportunities for hydro sector professionals

PennWell's Hydro Group is proud to offer daily business opportunities for hydroelectric powe...
African small hydropower

Partnership to advance small hydropower plant development in Africa

Hydroneo Afrique and African Infrastructure Investment Managers (AIIM) are partnering to dev...

Salini Impregilo inks US$575 million EPC contract for Georgian 280-MW Nenskra hydroelectric project

Salini Impregilo announced it has signed a US$575 million engineering, procurement and const...

Recent Comments




Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

07/01/2015
Volume 34, Issue 6
07/01/2015
Volume 23, Issue 4

Buyers Guide Products