Ohio firm named to rewind generator at 130-MW Barkley

NASHVILLE, Tenn., U.S. 10/18/11 (PennWell) -- The U.S. Army Corps of Engineers has awarded an $8.69 million contract to an Ohio firm to rewind generator No. 1 at the 130-MW Barkley hydroelectric project on the Cumberland River in Kentucky.

The Corps awarded the contract to National Electric Coil of Columbus, Ohio, to disassemble the generator, inspect and test bearings, replace stator windings and stator core, reinsulate damaged rotor poles, replace air coolers and piping, and reassemble the unit.

The Corps' Nashville District took bids for the work in September. The project is among nine Corps hydropower plants on the Cumberland that a study found need as much as $470 million in repairs.

Latest Slideshow

Your Picture Here: Send Us Your Dam Selfie

View Slideshow >>

more slideshows >>   

Hydro Whitepapers

There is no current content available.

Hydro Industry Financials

Most Read Articles

Recent Comments

Continuing Education

Professional Development Hours
To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

03/01/2015
Volume 34, Issue 2
1503HRcover
03/01/2015
Volume 23, Issue 2
1503HRWcover

Archived Articles

2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
Hydro Review Past Issues

Buyers Guide Products

Digital Governor Conversions and Retrofit Kits

Want to Go Digital? Over the last 10 years we h...

Standard & Expedited Bearing Repair Services

Our service and repair department is the longes...

Canyon Hydro Pelton Turbines

Canyon Hydro is a leading designer and manufact...

Manitou Falls 1999

1'st PTFE-lined thrust bearing shoes delivered ...

Buyers Guide Companies

Sauer Compressors USA Inc

Barr Engineering Co

ABB Inc/High Current Systems

JM Power Aggregates Ltd

Owner, inventor and distributor of an environme...

IC-Fluid Power Inc

Founded in 1989 to bring European fluid power t...