    The Bureau of Reclamation awarded a $458,534 contract to Peak Hydro Services of Chattanooga, Tenn., to repair draft tube discharge rings at the 86.4-MW Blue Mesa hydroelectric plant.

    The plant is part of the 1,747-MW Colorado River Storage Project near Montrose, Colo.

    Under the contract, Peak Hydro will repair draft tube discharge rings for Blue Mesa’s two Francis turbines. The turbine diameter is 10 feet, while the discharge ring diameter is 8 feet, 1 inch.

    The rings have been damaged by cavitation. A previous attempt by the installation of steel plates failed. Peak Hydro must remove remaining plates prior to weld repair and devise the best method to repair the damage.

    Hydro Industry Financials

    Buyers Guide Products

    Digital Governor Conversions and Retrofit Kits

    Want to Go Digital? Over the last 10 years we h...

    Standard & Expedited Bearing Repair Services

    Our service and repair department is the longes...

    Canyon Hydro Pelton Turbines

    Canyon Hydro is a leading designer and manufact...

    Manitou Falls 1999

    1'st PTFE-lined thrust bearing shoes delivered ...

    Most Read Articles

    Recent Comments

    Buyers Guide Companies

    Sauer Compressors USA Inc

    ABB Inc/High Current Systems

    Barr Engineering Co

    JM Power Aggregates Ltd

    Owner, inventor and distributor of an environme...

    Hydro Power Services LLC

    Provides service contractor specializing in fie...

    Continuing Education

    Professional Development Hours
    To access a course listing associated to a specific topic listed below, click on the topic of choice from the list below.

    12/01/2013
    Volume 32, Issue 10
    file
    11/01/2013
    Volume 21, Issue 6
    1311hrw-cvr

    Archived Articles

    2006 | 2007 | 2008 | 2009 | 2010 2011 | 2012 | 2013
    Hydro Review Past Issues

    Premium Content AD Promo Space