Portugal utility awards equipment contract for 260-MW Alqueva 2

Energias de Portugal (EDP) has awarded a 94 million euro (US$138.3 million) contract for supply of turbine-generators and other equipment for the 260-MW Alqueva 2 pumped-storage project on Portugal's Guadiana River.

Alstom Hydro, in consortium with EFACEC Engenharia S.A. and SMM of Portugal, won the contract to equip Alqueva 2, an expansion of the 260-MW Alqueva hydro project. Alstom supplied two 130-MW units to the original Alqueva pumped-storage project, which has been operating since 2004.

Alstom Hydro, a joint venture of Alstom and Bouygues of France, is to supply two 130-MW pump-turbines, motor-generators, and other mechanical equipment. EFACEC Engenharia and SMM are to be responsible for the balance of plant and installation at the site, respectively. Other equipment being supplied includes transformers, substation and interconnection, command and control equipment, and auxiliary equipment. The work is to be completed in early 2012.

EDP awarded a 50 million euro (US$79.3 million) contract in June to a consortium of Zagope Construcoes e Engenharia SA and Sociedade de Construcoes Soares da Costa SA to build Alqueva 2. (HNN 7/3/08) The pumped-storage addition to the multipurpose Alqueva project includes a water intake, tunnels, and a new powerhouse.

EDP announced in June that Portugal's competition authority cleared it to operate Alqueva and the 10-MW Pedrogao project, also on the Guadiana. (HNN 6/23/08) EDP agreed in October 2007 to pay 636 million euros (US$907.4 million) for a concession to expand the projects and operate them for 35 years. EDP has estimated it would invest 156 million euros (US$222.5 million) to expand Alqueva and Pedrogao.

Alqueva 2 is among ten new projects, and five hydro project expansions, included in Portugal's national program of dams with high hydropower potential, Programa Nacional de Barragens com Elevado Potencial Hidroelectrico. (HNN 8/6/08)

Related Articles

French city seeks construction, operation of Taconnaz small hydro project

The city of Chamonix-Mont-Blanc seeks bids to build and operate the Taconnaz small hydropowe...
IHA new hydropower report

International Hydropower Association releases 2015 Hydropower Status Report

The International Hydropower Association announces availability of its 2015 Hydropower Statu...

Proposed changes to U.K.'s FiT program met with backlash from small hydro sector

Changes to the United Kingdom's Feed-In Tariff program could have a negative impact on a num...

France inaugurates Le Croisic MHK test site

On Aug. 25, France officially inaugurated the Site d’ Experimentation en Mer (SEM-REV) at Le...

Recent Comments

Hydro Slideshows

more slideshows >>  

Hydro Whitepapers

Industry News

Editor's Picks

Volume 34, Issue 6
Volume 23, Issue 4

Buyers Guide Products